Delivering power connection stations for a large dry dock

Acting as an electrical acceptance testing partner, ABM diagnosed an installation gap and provided a highly custom, technical solution to solve the issue while protecting the the contractor’s schedule.

March 11, 2025
Read time: # minute

Transcript

Ship construction in a dry dock

A proactive solution to protect schedules, ensure safety, and avoid costly delays

When a major dry dock project hit an unexpected roadblock during electrical acceptance testing, the timeline—and millions in vessel maintenance operations—hung in the balance. Critical relays in the medium-voltage switchgear had not been programmed, jeopardizing the safe operation of the power system and threatening to delay energization. With multiple vendors stepping back and the clock ticking, ABM didn’t just identify the issue—they solved it.

Challenge

This dry dock supports critical maintenance, refits, and recommissioning of large, seagoing vessels. During preliminary evaluation of the upgraded power distribution equipment, the ABM acceptance testing team uncovered relays for medium voltage gear that had not been programmed.

The relays would not perform as intended without the programmed logic. Breakers would not trip when required, and the system would not safely and properly respond as designed.

With the gear manufacturer and the relay vendor responsible for limited deliverables, the electrical contractor faced an energization deadline without the relay logic needed to complete the necessary acceptance testing.

Solution

Relay programming was beyond the original project scope, but an ABM NETA IV Relay Field Engineer stepped up to protect the schedule.

A meeting with the end-user client confirmed the desired function. Knowing the relay’s technical requirements, the engineer developed and submitted logic for the relays. The electrical contractor approved ABM’s submission, and the field engineer programmed the relays, allowing the main switch gear to function as designed by the engineer of record.

With that hurdle behind the project team, acceptance testing could move forward for the medium voltage utility mains, feeders, main switchgear, and relays.

Benefits

The electrical contractor’s schedule was protected, and the end-user’s timeline was met. As an electrical acceptance testing partner, ABM committed to apply their experience with the overall project, the relevant safety requirements, and the client’s needs, to help the electrical contractor deliver a complete distribution system on time.

Pairing their complete picture of project needs with their experience handling logic problems for relays, ABM Electrical Power Solutions was able to diagnose the gap and provide a customized technical solution in a timely fashion.

Electrification deadlines were met. Safe function of electrical distribution equipment as designed was preserved. And costly construction delay penalties were avoided.

Partnering beyond the test

ABM didn’t just perform acceptance testing—they brought a full-picture understanding of the project, its safety requirements, and its operational goals. By identifying the gap, providing a custom solution, and executing with speed and precision, ABM helped this client move forward with confidence.

Need a technical partner who goes beyond the checklist?

Find out how ABM Electrical Power Solutions can help keep your project powered and on pace.